homework help 1048

Can someone please show me how complete the following question?

Question:Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for i = 1,…,5.

Write the appropriate constraint(s) for each condition. Conditions are independent.

a.   Choose no fewer than four projects.   

b.   If project 1 is chosen, project 5 must be chosen.   

c.   If project 2 is chosen, project 4 must not be chosen.   

d.   Projects cost 100, 200, 150, 75, and 300 respectively. The budget is 425.   

e.   No more than two of projects 2, 3, and 4 can be chosen.

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.